Walls are down, floor taken up and plastering done. Underfloor heating going in tomorrow.
Building Work – Project 3 – Week 8, Day 1
Steels across the back are in. Walls starting to come down.
Building Work – Project 3 – Weeks 6 and 7
Bit of a break up in Bamburgh for a week or so, in which time the roof was mostly finished off, Velux windows in and openings boarded up.
Building Work – Project 3 – Week 5, Day 3
Roof joists on. Steel beam welded in place above the doors. Tiler coming on Friday.
Building Work – Project 3 – Week 4, Day 3
Latest progress
Building Work – Project 3 – Week 4, Day 1
Scaffolding up. Some of the steel has arrived. Brickie back to finish off tomorrow.
Building Work – Project 3 – Week 3, Day 3
A few delays due to rain and Bank Holiday
Building Work – Project 3 – Week 2, Day 4
Walls starting to go up.
Building Work – Project 3 – Week 2, Day 2
Blockwork starting.
Building Work – Project 3 – Day 5
Concrete going in.