Building Work – Project 3 – Week 5, Day 3


Roof joists on. Steel beam welded in place above the doors. Tiler coming on Friday.
Latest progress

Scaffolding up. Some of the steel has arrived. Brickie back to finish off tomorrow.

A few delays due to rain and Bank Holiday

Walls starting to go up.